Project Taurus Project Status

Project Taurus / Colorado Springs / DEPN-26-0039

Status

Administrative approval, appeal timing, and pending Project Taurus records as of June 16, 2026.

Current as of June 16, 2026 Evidence dashboard

Status timeline

Approved at planning; not settled as an operating system

The City approval answers the planning question. Utility terms, permits, monitoring, appeal outcome, and operating performance still live in separate lanes.

  1. June 10, 2026 Administrative planning approval

    City planning staff approved the development-plan modification.

  2. June 11, 2026 Approval letter and plan set

    Approval letter and development-plan materials document conditions and follow-on work.

  3. June 16, 2026 Public-safe current status

    Appeal, CSU terms, final permits, sound monitoring, and operating records remain unresolved.

  4. June 22, 2026 Reported appeal deadline

    KOAA reported appeal requests are due by 5 p.m.; docket or no-appeal confirmation is still needed.

  5. July 16, 2026 Date-gated follow-on records

    Development-agreement and sound-monitoring work is date-gated in the approval record.

Supported by approval

What was approved

  • Development Plan Modification for Corporate Ridge Filing No. 1 Lot 4.
  • Planning-record approval for a BP-zoned, existing industrial/data-center site at 1565 High Tech Way.
  • Plan conditions tied to conformance, CSU construction drawings, landscaping/irrigation, financial assurance, development-agreement work, sound monitoring, and permits.

Still separate records

What was not approved

  • Final CSU utility terms, collateral, cost allocation, or energization schedule.
  • Actual water consumption, water bills, water-account history, or enforceable daily water cap.
  • Final building permits, state air permits, generator runtime records, or post-construction sound measurements.
  • Appeal outcome, operating performance, broad subsidy conclusion, or claim that no public impact is possible.

Process lanes

Where each unresolved claim belongs

Land record

Parcel and site facts

Parcel, ownership field, recorded plats, easements, and land-record context.

Planning

Development-plan modification

City Planning approval, conditions, amendments, and appeal.

Utilities

CSU service terms

Large Load Service Agreement, studies, line extensions, water/wastewater service, deposits, and cost responsibility.

Permits

Building and state permits

PPRBD permits, mechanical/electrical/plumbing work, air permits, and fuel-system records.

Operation

Measured performance

Measured water use, generator runtime, sound monitoring, complaint handling, enforcement, and remediation.

Project Taurus is approved at the administrative planning stage, but several important records are still pending or date-gated.